MEDIA ADVISORY
S.C. Department of Transportation
PHONE: (803) 737-1270
FAX: (803) 737-1273
Communications
RICHLAND AND LEXINGTON
COUNTY
ROAD CONSTRUCTION
INFORMATION FOR WEEK BEGINNING
Jan. 6, 2014
Expect delays, nighttime lane closures and periodic lane
shifts for a 10 mile work zone to widen Interstate 20 from Interstate 77 (MM
74.7) past Spears Creek Church Road (MM 84.6) in Richland
County. Completion is anticipated summer 2014.
Expect minor delays, flagging operations and possible
nighttime detours on Alpine Road (under I-20) between Faraway Drive and Polo
Road in Richland County while ramp intersections are being improved and I-20
bridges are being widened / reconstructed. Completion is anticipated
summer 2014.
Westbound traffic on I-20 between Spears Creek Church Road
and I-77 is shifted and will continue for approximately for 3 to 4
months. This shift will split the westbound motorists into two separate
lanes of traffic bordered by concrete barriers. The right lane will travel
adjacent to the westbound lanes and will be able to access all existing exits.
The left lane will travel adjacent to the eastbound lanes and will bypass the
Spears Creek Church Road and Clemson Road exits, but will have access to the
Alpine Road and I-77 exits.
Expect nighttime lane closures on I-26 from the I-77
interchange (mile marker 115) to S-6/Caw Caw Road. (mile marker 136) in both
the eastbound and westbound directions. Nightly lane closures will
continue through July 2015.
Expect sporadic delays to complete the work on US-1
(Gervais/Millwood/Two Notch) from the Congaree River to ½ mile past
Beltline Road. The anticipated completion date is January 2014.
Expect possible lane closures on Assembly St. (S-48) from
Pendleton St. (S-174) to Blossom St. (US 21/76) in Richland County for sidewalk
and ADA ramp reconstruction, traffic signal installation. Please note: NO LEFT
TURN onto Greene St. from Assembly St. heading Northbound or Southbound.
Anticipated completion date is Jan 10, 2014.
Expect lane closures and flagging operations on Hope Ferry
Road in Lexington between US-378 and Midway Road for a bridge replacement over
14 Mile Branch Creek. Construction is expected to be complete May 2014.
Expect lane closures and flagging operations on US 378 in
Lexington between George Street and West Butler Street for widening and
intersection improvements. Flagging operations and lane closures will
also impact West Butler Street, Reed Avenue, Old Chapin Road, US-1, and Park
Road in this vicinity. Construction is expected to be complete April
2014.
Beginning Oct. 21, 2013, Derrick Hollow Road between
DevilŐs Backbone Road and Derrick Park Road will be closed to through traffic
for phase two (final) of the bridge replacement over Hollow Creek. The
detour route will be DevilŐs Backbone Road, Dog Leg Road, Ridge Road and
Derrick Park Road. Signs will be posted marking this route. The
road is expected to re-open to through traffic Feb. 7, 2014. This site is
located approximately four miles northeast of Town of Batesburg-Leesville.
Expect minor delays and flagging operations on Broad River
Road from Greystone Boulevard to Lucious Road in Richland County for the
replacement of the bridge over the Broad River. This project will require
reducing traffic to one lane in each direction. The expected completion
date for the project is the summer of 2014.
####